Offshore Floating Production
Page 54
CHAPTER 4
Conversions, refurbishment and modifications
A Introduction
4.1 When an FP Contractor is invited to bid for a new project it has three options as to the vessel it may use. 4.2 First, it may have an existing asset. This may fit at least some of the technical requirements of the project. However, the stars rarely align quite so neatly. FP Contractors are not like commercial ship owners. An asset that is well suited to a new project may be unavailable, and it will almost certainly require some level of modification to meet the particular requirements of the reservoir characteristics, local standards, updated regulatory changes and so on. This may entail a complete replacement of the processing equipment and, in some instances, the required modifications will be very substantial. 4.3 Second, the FP Contractor can contract with a shipyard to build a new FPSO from scratch. This of course requires considerable investment and usually takes longer than upgrade, refurbishment or conversion work. 4.4 Third, the FP Contractor may convert an oil tanker or a floating storage unit (which it may already own, or which it buys in specifically) or, in the case of an FLNG unit, an LNG carrier. The FP Contractor will need to enter a substantial conversion contract, or separate contracts, each to cover the conversion work, module fabrication and final integration. Sometimes substantial changes are needed, not just to install the process train, but also to upgrade and convert the ‘shipping’ parts of the vessel, such as the hull, accommodation and engine systems. The final product may look quite unlike how it started and have completely different technical capabilities. 4.5 It is common in the offshore industry for projects to utilise an existing vessel which is converted for a new application or deployment, rather than build one from scratch. Similarly, refurbishment and modification are also common and may become increasingly necessary in order to meet new carbon emissions targets. Decarbonisation is already causing significant change in the industry. For example, new projects may require electrification of the FPSO itself and of the process train. If so, what is the source of that electricity? One trend is to utilise windfarm technology, including connecting to existing local windfarms (where possible) or even deploying dedicated floating turbines. There may be a requirement to use green fuel such as ammonia or hydrogen. All these changes may require substantial modifications of the power systems and engines used on traditional FPSOs. 4.6 In this chapter we will use the word ‘conversion’ to describe all types of conversion, modification and refurbishment projects.
B
Page 55
Conversions versus newbuild projects
4.7 There are many reasons why an FP Contractor may choose to convert an existing asset for a new project instead of commissioning a new FPSO. These include cost and speed. Conversion is in theory cheaper (for example less steel means a reduction in costs) and quicker (after all, much of the vessel is already built). If a conversion project goes to plan, an FP Contractor can be on field, and therefore earning, more quickly. Further, if the FP Contractor uses an existing asset, it does not have to pay to lay it up during the conversion phase.
4.8 However, as relatively straightforward as this may sound, some of the most hard-fought conflicts involving FPSOs have been conversion and refurbishment disputes. The situation is not unlike a time-critical renovation of an old house. The walls and the foundations may be sound (or at least appear to be so). The builders may well say they cannot quote for a particular part of the work until the plaster is removed, or the floorboards taken up. And then, when the plaster comes off or the boards are pulled up, the builders encounter something unexpected which adds time and money to the renovation works. The homeowner becomes frustrated (was this included in the price?) and the builders may well be too (have they quoted a lump sum or promised someone else that they can start on another job for which they will now be late?). Often the houseowner might lament that, on reflection, they would have been better off buying new, or simply knocking down the house and starting again.
4.9 FPSOs are complex, high-value assets and it is not difficult to see how, for example, a contract for the conversion of an existing asset can quickly turn sour. It is a similar story for conversion of LNG carriers to floating liquefaction facilities. As such, the FP Contractor should be careful to ensure that there is as much certainty as possible in the terms of its contract with the EPC contracting yard or yards.1
4.10 In this chapter we explore some of the pitfalls, and consider key contractual provisions, specific to a conversion project. To do so we examine the different stages of such a project, starting with finding the right vessel (and its suitability for the proposed work) through to delivery under the construction contract and post-project.
Page 55
C Acquisition of vessels
(i) The vessel for conversion
4.11 First, the FP Contractor needs a vessel to convert. This may be an existing FPSO; it may be an oil tanker. The FP Contractor may already own the vessel, but it may need to go into the market to buy one. In the latter situation, a key issue between the FP Contractor and the seller is the allocation of liability for the condition of the vessel at the time of purchase, and its suitability for the proposed conversion work. 4.12 This needs to be adequately covered in the acquisition contracts. Risks inherent in acquiring vessels for conversion were illustrated in the case of Kellogg Brown & Root IncPage 56
Page 57
(ii) Incorporating the vessel into the design
4.18 Turning to the conversion process itself, how will the buyer (now the owner) of the existing vessel and the conversion yard deal with potential issues arising from the suitability of the vessel for the basis of design for the conversion? The vessel to be converted may have been selected after the preliminary design was prepared. The design will need to be developed before the chosen vessel arrives at the construction yard, based on the vessel’s as-built drawings. Verification will be needed that those drawings have been revised to take into account any repairs or modifications to the vessel during what may be a long trading history. Further, do the as-built drawings include all the information needed to complete the design? And what if the vessel or its equipment are materially different from the assumptions made in the preliminary design? The drawings would not indicate the current condition of the vessel. What if condition issues come to light upon arrival at the yard and this affects the planned conversion schedule (e.g. delay due to steel renewal, as in Kellogg Brown, or an unexpected aspect to the vessel’s design that makes it impossible to enter dry dock)? The yard will want to allocate this liability to the owner and will want any additional work required due to unforeseen condition issues to be dealt with as a ‘variation’ to its work, with knock-on cost and schedule adjustments. 4.19 Fundamentally, the question is: who is responsible for ensuring that the vessel used is suitable for conversion to a fully functioning FPSO? In a newbuild project, it is perhaps more reasonable to expect a yard to be solely responsible for unexpected work. However, where an existing vessel is procured by an owner for a conversion, the yard may well feel entitled to make the owner responsible for any surprise issues that arise as a result of that vessel’s condition.4D The yard, scope of work and delivery
(i) One yard or two?
4.20 Once the FP Contractor has a vessel to convert, it will need a construction yard to carry out the work. This does not necessarily mean that there is only one yard. It mayPage 58
(ii) Scope of work and fitness for purpose
4.22 The contract between the FP Contractor and the conversion yard is likely to be substantial, with detailed provisions on, for example, allocation of risk, the technical specification, pricing and variation work. A central issue is: does the scope of work include everything necessary to achieve the functional requirements of the basis of design? Here the FP Contractor finds itself in a precarious position. The ultimate client, the Company, (i.e. the charterer) will insist that the FPSO must achieve various performance and production criteria, both at the start of the charter (i.e. for acceptance) and going forward (i.e. as the basis of payment of hire).5 4.23 The FP Contractor’s obligation may be limited to verifying the ‘constructability’ of the design. Opinions may vary on precisely what this means, but it is generally understood to mean that the design is fit for performance of detailed engineering, but not necessarily fit for the purposes of the contractual functional requirements.(a) Robin Rigg case study
4.24 It is helpful at this stage to consider the Supreme Court’s decision in MT Højgaard A/S v E.ON Climate & Renewables UK Robin Rigg East Limited and another 6 This case illustrates the issues surrounding the extent of the yard’s obligations in terms of whether the FP Contractor produces a vessel which conforms with the functional requirements of the contract (i.e. it does what it is supposed to do), as opposed to simply complying with the technical specifications in the contract. In May 2006, E.ON invited tenders to construct foundations for two offshore wind farms at Robin Rigg in the Solway Firth. MT Højgaard (“MTH”) were the successful bidders to design and install the foundations. Shortly after completion, the foundations failed. The issue was whether MTH was liable for the failurePage 59
Page 60
(iii) Delivery of the vessel to the yard
4.31 It is perhaps stating the obvious that, in order to perform construction work as planned, the vessel needs to arrive at the conversion yard on time. The FP Contractor will be obliged to deliver the vessel in accordance with the schedule set out in the conversion contract, which ought also to allocate the consequences of any delay. There may be added complexity if the vessel to be converted is not in the FP Contractor’s ownership at the time when the contract is agreed. 4.32 It is equally obvious that the yard must be ready to perform the work. In some circumstances, the FP Contractor may have a contractual right to cancel the vessel’s arrival entirely if the yard is not ready by the agreed deadline. One extreme illustration of this, from the cruise vessel market, was the dispute in 2000 between the Liverpool shipyard Cammell Laird and the Italian cruise line Costa Cruises. Costa contracted with Cammell Laird to lengthen its cruise ship Costa Classica by inserting a 45-metre new section amidships. The yard commenced work on the new section. However, when the yard failed to keep precisely to the contractual schedule, Costa cancelled the contract, even though the new 26,000-tonne section was almost complete and the vessel was already on its way to Liverpool. Whilst the exact details are confidential, a subsequent arbitration found that Costa had been entitled to terminate and Cammell Laird was ordered to pay damages. Cammell Laird went into receivership in 2001. 4.33Page 61
E Pricing
4.35 For any kind of conversion/modification work, a number of pricing models are available to the parties, ranging from a pure ‘time and materials’ basis to an all-inclusive lump sum. For the FP Contractor, the more up-front clarity on pricing the better. For the yard, however, this may entail too much risk. For example, what if a project is expedited and parts of the work are not fully scoped at the time of contract signing? What if there are contractual variations to the work? The question then is: how will the extra work be identified and priced? 4.36 The yard contract is likely to include detailed provisions setting out what work is included within the lump sum and what work is not (if it does not, there is likely scope for dispute). It may also include some estimates on quantities which are then remeasured with actual quantities once the work has been completed. 4.37 Typically, in addition to the lump sum element, the conversion contract may include:- • A detailed schedule of agreed rates, often called ‘unit rates’;
- • Details of the work to which those rates shall apply; and
- • Aspects of the work that are to be ‘remeasured’, such that estimated quantities are replaced with actuals.
We explore each in turn, before turning to an alternative pricing (and contractual) model that is the ‘target sum’ contract.