Offshore Floating Production
Page 185
CHAPTER 12
Decommissioning
A Introduction
12.1 Decommissioning projects entail many of the same risks as offshore construction projects, including the risks associated with conducting large and complex operations at sea in varying weather conditions, personal injury, property damage and pollution. However, decommissioning projects also entail some unique challenges and risks, including those associated with:- 1. Disposal of a large volume of waste material;
- 2. Handling and disposal of hazardous materials;
- 3. Fully identifying the facility, equipment, materials and substances to be removed from the field; and
- 4. Increased reputational risks.
- (B) FPSO decommissioning projects and contracts;
- (C) Reputational risks;
- (D) International obligations on the decommissioning of offshore installations;
- (E) EU Regulations applicable to the decommissioning of offshore installations;
- (F) UK domestic legislation and regulations applicable to decommissioning of off-shore installations.
B FPSO decommissioning projects and contracts
12.3 The decommissioning of an offshore field where a FPSO has been deployed will often be undertaken in the following stages:- 1. Planning;
- 2. Cessation of production;
- 3. Flushing of the risers and subsea pipelines;1
- 4. The disconnection and removal of the FPSO from the field;
- 5. Permanent plugging and abandonment of the wells;
- 6.
Page 186
- 7. Seabed clean up.
(i) The disconnection and removal of the FPSO from the field and recycling of the FPSO
12.5 If the FPSO is owned by an FP Contractor and contracted onto the field by the operator then it is likely that the FPSO charter will specify the extent of the FP Contractor’s obligations to remove the FPSO at the end of the contract (or the operator’s obligation to redeliver the FPSO at the end of a bareboat charter). In this context the FP Contractor’s contractual obligations are often referred to as demobilisation (rather than decommissioning) obligations. The demobilisation of the FPSO is however part of the decommissioning of the entire field. 12.6 The FPSO charter will often require a demobilisation plan to be developed to detail the activities, required resources, schedules and responsibilities in order to conduct a safe and timely demobilisation. The FP Contractor may accept the responsibility for the demobilisation of the FPSO including disconnection activities, retrieval of the mooring system, disconnection of the risers and towing the FPSO out of the field. The FP Contractor will procure support for such activities from specialist offshore contractors who own the specialist vessels (including tugs and anchor handlers) necessary to perform the work. 12.7 The Company will often be required to provide the necessary vessels or facilities for receiving any processed oil remaining on board the FPSO. The charter may require the FP Contractor to dispose of the residual slops including those remaining in the oil storage tanks post discharge of the oil cargo. The Company may agree to pay the FP Contractor a lump sum demobilisation fee or to pay for the FPSO’s documented costs of demobilisation to a named place (such as a local port). 12.8 From a UK regulatory perspective, OPRED2 guidance recognises that there may be a requirement to remove an FPSO from a field in advance of the approval of a decommissioning programme (e.g. because the FPSO charter has come to an end before the Company has prepared the decommissioning programme). In these circumstances, removal of the FPSO can be agreed through an exchange of correspondence between the operator and OPRED. This is treated as a partial decommissioning approval. The documentation should detail all decommissioning activity to be undertaken in order to release the FPSO from its offshore operating location and move to the next location. If dismantlement is the most likely end point for the FPSO then the OPRED guidancePage 187
- 1. Refurbishing or upgrading the FPSO in order that it may be redeployed to exploit other opportunities as an FPSO; or
- 2. Scrapping, dismantling, recycling or decommissioning of the FPSO.
(a)
Page 188
Illustration 1 – North Sea Producer FPSO
12.14 The MacCulloch field in UK Central North Sea was developed in 1996/97 and had an expected life of ten years. Production commenced via the North Sea Producer in August 1997. This vessel was owned by the North Sea Production Company (NSPC) (a joint venture between Maersk and Odebrecht).
12.15 The North Sea Producer was disconnected from the MacCulloch field infrastructure in 2015. The works were conducted following an exchange of correspondence agreed with OPRED. Thereafter, the vessel was taken to Teesside by the owners for possible future re-use. The FPSO was then sold in 2016. The FPSO was cleared to leave the UK for further work in Nigeria, but was towed by the buyer to Chittagong, Bangladesh, a place well known for shipbreaking using poor health and safety practices and little (if any) environmental controls.
12.16 The NSPC claimed it had sold the vessel to a third party for redeployment and that it did not know the FPSO would be scrapped in Bangladesh. However, in November 2019 a court in Bangladesh ruled that the import, beaching and shipbreaking of the North Sea Producer in Bangladesh was illegal.
12.17 There are lessons to be learnt from this case. Where an FPSO is being sold ostensibly for future redeployment by a third party then the seller should conduct due diligence on the buyer. If the buyer is not in the business of operating FPSOs, the seller should be particularly wary about proceeding with the proposed sale. The seller may also wish to (i) include an ‘anti-recycling/scrapping’ clause in the sale agreement; (ii) require the buyer to indemnify the seller for all consequences of breach; and (iii) require security for the buyer’s compliance with its obligations. If in any doubt, it should be kept in mind that the reputational risks of the FPSO ending up beached in Bangladesh may outweigh the benefits of the sale. Further, there may be the risk of criminal sanctions on the seller and its officers (including fines and imprisonment) where the vessel is sold to a middleman and then on-sold for scrapping.4
Page 188
(ii) Well plugging and abandonment
12.18 The plugging and abandoning of wells is a significant part of any decommissioning project and of its total cost. It will typically be performed by drilling contractors using drilling rigs, although some well plugging can be performed by specialist well intervention vessels. The hire of drilling rigs for this work is likely to be done on a drilling contract form such as the IADC offshore form,5 a modified LOGIC drilling contract form6 or the oil company’s/operator’s standard drilling contract form.(iii) Removal, dismantling and disposal of subsea facilities including Christmas trees, pipelines etc.
12.19 The contracts to remove the physical installations from the field other than the FPSO itself are commonly referred to as decommissioning contracts. 12.20Page 189
- 1. Personal injury to employees of the Contractor Group;
- 2. Damage to Contractor Group property;
- 3. Personal injury and damage to the property of any third party to the extent that any such injury, death or disease or loss or damage is caused by the negligence or breach of duty (whether statutory or otherwise) of the Contractor Group;
- 4. Pollution emanating from the property of the Contractor Group including Contractor Group’s vessels; and
- 5. Consequential losses suffered by the Contractor Group.
- 1. Personal injury to employees of Company Group;
- 2. Damage to Company Group property;
- 3. Personal injury, death or disease or loss of or damage to the property of any third party to the extent that any such injury, loss or damage is caused by the negligence or breach of duty (whether statutory or otherwise) of a member of the Company Group;
- 4. Pollution emanating from the property of the Company Group; and
- 5. Consequential losses suffered by the Company Group.
Page 190
- 1. ‘Technical Information’: as this is not ‘rely upon’ information, the Company makes no guarantee or warranty, express or implied, as to the correctness, adequacy, sufficiency and consistency of such technical information. The FP Contractor is generally not entitled to any variation order (or other remedy) in relation to any incorrectness, inadequacy, insufficiency or inconsistency in such technical information; and
- 2. ‘Rely Upon Information’: if the rely upon information is incorrect or inconsistent and has an impact on the “Services”,9 the FP Contractor is entitled to submit a variation order.
C Increased reputational risks
12.29 In addition to complying with legal requirements and entering into appropriate contracts for the work, the successful decommissioning project will also have close regard to reputational risks from an early stage. Decommissioning entails the disposal of large amounts of materials, some of which are hazardous, and this can naturally attract significant public attention and therefore the risk of reputational damage. Irrespective of the scientific and legal merits, decommissioning projects will not be successful if the Company’s reputation is damaged as a result. 12.30 The Brent Spar is the case in point. The Brent Spar facility (an oil storage and tanker loading installation) was operated by Shell. Following the end of its useful life,Page 191
D International obligations relevant to the decommissioning of offshore installations
(i) United Nations Convention on the Law of the Sea (UNCLOS)
12.35 UNCLOS was adopted in 198212 and provides that offshore installations which are abandoned or disused shall be removed. Article 60(3) states:Any installations or structures which are abandoned or disused shall be removed to ensure safety of navigation, taking into account any generally accepted international standards established in this regard by the competent international organisation. Such removal shall also have due regard to fishing, the protection of the marine environment and the rights and duties of