Offshore Floating Production
Page 20
CHAPTER 2
FPSO design
A Introduction
2.1 In this chapter, we look at particular requirements regarding the design of FPSOs – whether for a newbuild or a conversion project. An FP Contractor’s choice of a newbuild or a conversion is addressed in , but here we examine how the division of responsibility relating to vessel design and the inevitable changes to design parameters that occur during the development of an FPSO project are handled in the case of a typical FPSO charter and how they affect the construction subcontract. 2.2 Each FPSO is different. There may be major variances in the hull structure. For example, in addition to production equipment being installed onto a traditional ship shaped vessel, a concrete or steel barge hull may be used, or a circular hull may be employed. Some spar and semi-submersible hulls have also been equipped with limited oil storage. Different types of mobile production unit, including FLNGs, are described in more detail in , Part (ii), with an evaluation of the choices in , Part (iii). Even if the whole structure of the FPSO is generic, the production equipment and other key features may vary considerably. 2.3 The reason behind the differences, and the bespoke nature of an FPSO design, is the specific requirements of the field at which the FPSO is to be deployed. These requirements are usually identified in a ‘basis of design’ which is prepared by the Company to identify the characteristics of the unit that will be needed to provide continuous production in the relevant conditions. The reasons for variations in those requirements, even between fields within a similar location, include characteristics of the reservoir(s), wellhead temperatures and pressures, the gas/oil ratio, viscosity, density and wax content. The reservoir properties, combined with the number and placement of the wells, dictate the expected volumes of production and quantities of oil, gas and water. These change over time and may require volumes of water or gas to be injected to support production. In addition, the selected subsea architecture, water depth, metocean conditions, distance from shore and local regulatory regimes all influence the design of the FPSO. All these factors are taken into account in the preparation of the basis of design.1 2.4 From this, the functional requirements of the production unit will be drawn up, identifying the key performance characteristics required to enable continuous production of the expected volumes at the site in the prevailing conditions. A description of the keyPage 21
B Design responsibility
2.6 The precise extent of an EPIC contractor’s responsibility to develop a Company-provided preliminary design into a complete design capable of achieving the functional specification requirements is covered in detail in legal texts on offshore construction.2 The purpose of the current text is to examine the FP Contractor’s obligations to procure and deliver a unit capable of achieving the technical requirements under the FPSO charter. 2.7 A crucial feature of the successful performance of the FP Contractor’s obligations is the performance of its major subcontractors. For example, the FP Contractor may develop (perhaps with assistance from a design subcontractor) the technical requirements of the basis of design into a FEED (front end engineering design) or other standard of preliminary design.3 The FP Contractor may then transfer the responsibility to complete the design to a construction subcontractor, whose task it will be to develop the design to the level required to achieve the functional requirements.4 If the construction subcontractor fails to do this successfully, the FP Contractor would be exposed to liability to its Company client under the charter terms for failure to procure the unit to meet the functionalPage 22
C The design development process
2.9 The Company will usually prepare a functional specification and sometimes a concept design, derived from its basis of design, based on its study and analysis of the characteristics of the reservoir and the field, the metocean conditions and its objectives for production. This will form the basis of the scope of work to be contracted to the FP Contractor under the FPSO charter terms, either in a comprehensive charter for the provision of FPSO services, or split between a lease of the FPSO and a contract for the provision of O&M services. If the latter structure is chosen, the requirement for the provision of an FPSO capable of meeting the requirements of the basis of design will be contained in the lease, and the O&M services obligations will commence once the FPSO has successfully been provided and is ready for operations. 2.10 A functional specification is derived from the basis of design. The fundamental requirement is for the FPSO to be capable of achieving each of these functionalPage 23
Page 24
(a) Illustration 1 – off-spec hydrocarbons
2.17 The scenario: The basis of design includes an analysis of the characteristics of the reservoir hydrocarbons. The FP Contractor provides an FPSO designed to process hydrocarbons with these characteristics, which then fails to achieve the required processing targets. The FP Contractor alleges that the reason for the shortfall is an alteration in the characteristics of the actual hydrocarbons produced, compared to those described in the basis of design. 2.18 The issues/arguments that might arise: This would give rise to disputes of a technical nature concerning whether the hydrocarbons are truly outside the design parameters, and whether, even if the hydrocarbons are off-spec, this is the cause of the shortfall. The Company would usually require the FP Contractor to prove that if the hydrocarbons had been within spec, the design would have been sufficient to achieve the target production. However, the important legal issue here is whether, by including the hydrocarbon characteristics in the basis of design, the Company has warranted their accuracy, or accepted responsibility if the actual hydrocarbon characteristics are different. As noted earlier, it is rare for an explicit warranty of the accuracy of the Company-provided information to be given. The Company would argue that in the absence of any explicit warranty, no implied warranty may be assumed. The information has been provided in good faith, and represents the Company’s knowledge at the relevant time, but no promise has been given that the actual hydrocarbons will match entirely the characteristics shown. 2.19 The FP Contractor would nevertheless argue that as the characteristics have been included in the basis of design, it should not be penalised for the consequences of the work to be performed being different from its contractual scope of work. The Company would counter with an argument that all that is needed is for the FP Contractor to providePage 25
(b) Illustration 2 – weather loading windows
2.23 The scenario: The Company’s functional requirements specify the weather conditions within which the FPSO must be capable of offloading product to an offtake vessel. This is a vital aspect of the design. If the storage capacity has been calculated on the assumption of regular offloading without delays due to bad weather, there is a risk of storage tanks becoming full, leading to suspension of production, if the prevailing weather conditions at site are worse than contemplated in the functional requirements. The vessel may have successfully passed offloading tests, but subsequently may be prevented from offloading as planned due to weather conditions being worse than anticipated. 2.24Page 26
(c) Illustration 3 – design assumptions
2.26 The scenario: As mentioned, the preliminary design or FEED may be based on various estimates, calculations and other assumptions, to be verified by the FP Contractor during the design development process. A key assumption in the development of a floating production system is the centre of gravity (COG) of the unit topsides, which is essential to the stability of the vessel. The COG may vary according to the height, weight and layout of the topside equipment to be added to the vessel hull. The design may have been well-developed, with long lead items of procurement already designed and ordered, before it becomes apparent that the assumption on which the COG has been based is incorrect. This may have anticipated a lower height, weight and distribution of topsides than the FP Contractor determines is necessary to achieve the level of production required for processing the hydrocarbons with the characteristics shown in the basis of design. The miscalculation of the COG may have an effect on the overall stability of the vessel, but also may affect the operating parameters of the equipment to be installed. 2.27 The issues/arguments that might arise: The Company would argue that the design of topsides equipment to meet the estimated COG falls within the responsibility of the FP Contractor. This may be correct to the extent of available choices in design and layout. However, the FP Contractor may argue that whatever design is chosen, the functional requirements of the charter cannot be met due to the hull being insufficient to bear the weight and volume of processing equipment required to achieve the target volume production. 2.28 The solution: To overcome this difficulty, it may be necessary to increase the size of the hull, which would obviously be a major departure from the intended scope of work, with substantial delay and additional costs. Alternatively, stability may be improved by increasing the capacity of ballast storage, with a proportionate reduction in the capacity of cargo storage. The consequence of this would be failure to achieve one of the essential functional requirements of the unit; reduced storage may have a direct effect on the ability of the FPSO to achieve continuous production of the target volume. The third solution may be a total redesign of the topsides, equipment and materials to be used, which inevitably would have a major effect on costs and schedule, with the addedPage 27
D Changes to basis of design
(i) Changes – some issues and illustrations
2.30 As mentioned in Illustration 3, the inherent limitations in a floating production design development relating to weight, height, layout and stability may require changes to the basis of design or other technical requirements imposed by the FPSO charter terms. There may be more than one proposed technical solution. Without the certainty that any of the proposed solutions will achieve entirely what is required, often a substantial period of design reassessment occurs before an acceptable solution is adopted. In such a case, the question arises whether the FP Contractor is entitled under typical FPSO charter terms to put on hold the design development process pending such reassessment. In many instances, such a suspension would be advisable from the viewpoint of wasted costs; in Illustration 3, long lead items had already been ordered before the design had been completed. A suspension may also be desirable to minimise delay to the overall schedule. If work proceeds before the design is complete, the time taken for rework may be greater than if the work had paused pending the completion of design. 2.31 The FP Contractor’s entitlement to suspend the work pending a design reassessment may be included in the detail of the charter terms. However, assuming the point is not specifically addressed, the question arises whether the FP Contractor would be in breach by suspending work. The Company, which may be anxious to ensure that work is completed as quickly as possible, may complain that the suspension is in breach of the FP Contractor’s obligation to proceed with the work with all due despatch. The charter terms would usually include a provision whereby, following notice by the Company, failure to continue the work with due diligence may lead to termination. However, the FP Contractor would argue that in suspending work until the design is reassessed and completed, it is indeed proceeding with all due diligence. Quite apart from any argument that responsibility for the defect which requires the design reassessment flows from the preliminary design, the charter does not give the Company the authority to order the sequence in which work is performed. Rather, the charter would ordinarily impose liquidated damages for failure to meet target completion dates with the risk of termination if agreed deadlines are not then met. Thus, it is the FP Contractor’s responsibility to determine how best to achieve those target dates and deadlines in order to avoid the burden of liquidated damages or termination. 2.32 The more difficult question may be to determine the FP Contractor’s entitlement to insist on making a change to the basis of design. The Company’s rights to impose changes are dealt with in concerning contractual variation procedures.10 SuchPage 28
(a) Illustration 4 – insufficient buoyancy
2.34 The scenario: The Company-produced FEED defined the hull as a semi-submersible platform of a particular size, onto which various specified topsides equipment was to be installed; it also specified a minimum deck load requirement. The FP Contractor accepted responsibility to complete the design to achieve the charter specification and subcontracted remaining design work to its construction subcontractor. The construction subcontractor calculated that the semi-submersible hull had insufficient buoyancy to carry the specified equipment and achieve the minimum deck load. It therefore proceeded to undertake major changes to the design, incurring substantial additional time and costs, for which it held the FP Contractor responsible. 2.35 The outcome: The FP Contractor was unable to hold the Company responsible for producing a preliminary design which was incapable of being achieved, as it had accepted full responsibility for that design in the charter terms.(b) Illustration 5 – relaxation of design requirements
2.36 The scenario: The charter technical requirements imposed detailed specifications concerning the thickness of hull steel for two FPSOs undergoing conversions from tankers. The oil company wanted to ensure that each FPSO was capable of continuous operations at the field for a minimum of 20 years, without dry docking. It included in the specification its standard for minimum hull steel thickness for a 20-year charter. The two tankers chosen for conversion had suffered pitting to cargo tanks, with reduced steel plate thickness in certain areas. The vessels nonetheless achieved the highest classification standard, which the FP Contractor considered was sufficient for the Company’s purposes and due to the as-built thickness of steel plate, had substantial residual thickness notwithstanding the pitting. 2.37 The FP Contractor proposed to the Company that the work should be performed in accordance with a specification for steel renewals which was sufficient to achieve the charter objectives of 20 years’ life of field without dry docking, even though the steel plate renewals fell short of those required to comply with the Company’s standard. ThePage 29
(ii) Charter amendments
2.39 In each of the preceding illustrations, the FP Contractor’s preferred method of recourse was to place responsibility for design changes on its subcontractor, rather than to confront its Company client to accept responsibility for those changes. This is understandable in the commercial context. The Contractor has a long-term relationship with its Company client, and a short-term relationship with its construction subcontractor. Also, it is often the case that an FP Contractor under a charter faces a heavy burden for the risks of design development, which it then passes to its subcontractor under the construction subcontract, each being a turnkey contract whereby design risk, in the absence of any provision to the contrary, rests with the respective contractor.11 Additional reasons are as follows:- • The FP Contractor’s obligation under typical FPSO charter terms, whether that be a conventional time charter, a lease or an operating agreement imposing the obligation to procure a vessel, is conditional upon it providing an FPSO which meets the specification requirements; it is not simply a services, or O&M, agreement whereby a contractor is remunerated for the services it provides. As a consequence, unless the FPSO meets the acceptance requirements, the charter period does not commence.
- • In the event of delay in achieving the turnkey obligations, the FP Contractor faces substantial penalties in the form of liquidated damages or, in a worst-case scenario, termination. Therefore, insofar as there is uncertainty as to the appropriate method of achieving requirements of the basis of design, the burden of delay caused by design uncertainty and the need for a reassessment requiring the Company’s consent rests on the FP Contractor. Inevitably, to avoid delay caused by design uncertainty, the FP Contractor may choose to adopt the more expensive option to mitigate the risk of liquidated damages, or worse, termination.
- • The FP Contractor may consider that the Company should consent to changes in the basis of design or relax its specification requirements in accordance with a duty of good faith. This duty is considered in more detail in but in short, English law does not impose such duty where the contract contains detailed terms governing the subject of the potential dispute. In typical charter terms, the contract contains sophisticated provisions concerning variations to the work, as discussed in Sections J, K and L and in .
Page 30
(iii) Charter notice requirements
2.41 The third major legal issue arising is the usual requirement under a charterparty for the consequences of changes to the basis of design to be notified promptly. As set out earlier, it is normally the case that although the FP Contractor under the terms of the charter takes on EPIC responsibilities, it will subcontract a substantial part, if not all, of that responsibility to a third party. Defects in the basis of design may not become apparent until a late stage in the development of the design, possibly following procurement of long lead items. The construction subcontractor may raise claims based on the terms of the subcontract, which the FP Contractor may wish to reject. As the main focus of work activities at that time would be the performance by the subcontractor, the ultimate consequence of its underperformance may be the FP Contractor’s failure to deliver the work to the Company’s satisfaction on time and in accordance with the FPSO charter. Therefore, it would be natural for the FP Contractor to reject its subcontractor’s claims for additional costs and schedule extension and to insist on expedited completion. However, in so doing, it is important that the FP Contractor should have an eye on its potential remedies under the FPSO charter. 2.42 Although the FP Contractor may dispute its subcontractor’s claims, these should nevertheless be notified to the Company in accordance with the notice requirements of the charter as though they were valid, in order that the FP Contractor may reserve its right to claim additional costs and schedule extension under the FPSO charter terms, in the event that the subcontractor successfully establishes its entitlement. 2.43 Under English law this ‘back-to-back’ method of contract management is well-understood. The FP Contractor, being piggy in the middle, is entitled to dispute its sub-contractor’s claims for additional costs and schedule extension, whilst at the same time relying on its subcontractor’s claim as grounds for an equivalent compensation under the charter terms.12 2.44 Failure to meet the charter notice deadlines may be fatal to the FP Contractor’s claim for an indemnity from the Company for the costs that the FP Contractor has suffered under its subcontract with the construction subcontractor. Thus, if the construction subcontractor continues to pursue its claims for additional costs, and ultimately succeeds against the FP Contractor, due to changes in the basis of design that are the Company’s responsibility under the charter, the FP Contractor may risk the loss of its rights to compensation under the charter, even though its liability to the subcontractor is caused by the Company. Therefore, the charter notice provisions require close scrutiny. 2.45Page 31
Page 32
E Design integration
2.50 A particular feature of developments in floating production is the integration of processing and ancillary plant onto a vessel hull: oil and gas technology combined with conventional marine engineering. This presents two principal concerns: one is the integration of contrasting philosophies into an overall FPSO design, and the other the procedure for installation of topsides on to the hull. 2.51 Technical issues are described in , Part (iv) (Technical definition and design phases). The legal issues relevant to design development concern allocation of responsibility between the various parties involved.(i) Allocation of design risk
2.52 The various parties involved in design development may include:- • The Company who produces the original basis of design and the engineering product such as FEED and any design subcontractor appointed by it;
- • The FP Contractor who is responsible to develop that design under the charter terms, and any design subcontractor appointed by it;
- • Vendors and manufacturers of major equipment;
- • The designers and suppliers of specialist mooring equipment such as turrets and swivels;
- • The fabricators responsible for delivery of topsides modules (which may not be delivered under EPIC terms);
- • The shipyard responsible for the fabrication or conversion of the hull;
- • The shipyard responsible for the integration of topsides equipment on to the hull;
- • The shipyard (in the case of an EPIC contract) with overall responsibility to deliver a fully functioning FPSO;
- • Owners or licensees of intellectual property in the design.
Page 33
(ii) Separate hull and topsides yards
2.57 Another particular feature of the design of FPSOs and similar vessels is the prospect of the hull being fabricated or converted at one shipyard and removed to a second shipyard for the installation of topsides equipment. The reason for this may be that the cost of fabricating or converting the hull in one yard is cheaper than the vessel being builtPage 34
(a) Illustration 6 – interface design
2.58 The scenario: The FPSO design was developed in the usual way from a basis of design to a detailed specification. During design development, a shipyard in Singapore was contracted to build the hull and accommodation, and to complete the marine engineering design, and a yard in Norway was selected to install the topsides equipment. Those parts of the specification concerning installation of topsides equipment were incorporated into the scope of work of the Norwegian yard. Following completion of the hull and accommodation in Singapore, the vessel was transferred to Norway for completion, requiring delivery on location at the North Sea field. A number of difficulties were encountered, including the fact that the work performed in Singapore was found to be inadequate for the purpose of installation of topsides as contemplated in the specification agreement with the Norwegian yard. In short, the detailed design required for the adequate installation of the topsides on the hull structure fell between the gaps of the two design development processes, one being for the marine systems in Singapore, and the other for the oil and gas systems in Norway. This issue formed part of a larger dispute concerning the compliance of the FPSO with Norwegian regulatory standards, which is covered in more detail in the case study in .16(b) Illustration 7 – handover design
2.59 The scenario: The FPSO’s hull and accommodation block were completed in Korea and transferred to the North Atlantic for installation by a yard operating under local content requirements. The topsides design included stainless steel piping for the fire water safety system. The design anticipated the removal of sections of the fire water system delivered with the hull in order for installation and integration of the topsides equipment and connecting pipework. Therefore, the hull firewater system design incorporated sections of temporary piping which, to save cost, used only carbon steel. During the installation and integration work, it was discovered that the interaction of saltwater with the temporary carbon steel had caused corrosion which then caused damage and blockages in the components of the firewater system, such as deluge nozzles and valves. The rectification work was performed by the local content yard, at a far greater expense than if the work had been performed in Korea. The desire to save cost for a temporary element of the hull scope meant that the overall project cost was increased significantly.
F
Page 35
Location
2.60 We consider in the role of warranties of fitness for both general and particular purposes.17 A typical FPSO charter contains a number of specific warranties that, although not labelled as fitness for purpose, may nevertheless fall into that category, the most common being those concerning the place of operations.
2.61 The FP Contractor may be required to warrant the FPSO is capable of operating at the designated location, often identified by reference to the block in a particular field. The FP Contractor would wish to avoid giving a warranty that extends further than compliance with the requirements of the basis of design; for reasons mentioned in paragraph 2.3, the obligation to ensure the basis of design is suitable for the particular requirements at the location would usually rest on the Company. This would contrast with the FP Contractor’s obligation to comply with the basis of design in order to ensure the FPSO is capable of operating at the location. An obligation of this nature would place on the FP Contractor the burden of filling gaps in the basis of design to achieve its objectives, but not to change the basis of design to make it fit for purpose.
2.62 The location provisions may include the possibility of the FPSO being relocated to a field outside the designated block. These relocation provisions are rarely anything more than an agreement to agree – not enforceable obligations. The parties may be obliged to discuss terms for relocation in good faith, but an obligation to agree cannot be extrapolated from a duty to negotiate; in each case, neither party is obliged to put the commercial interests of the other party ahead of its own.
2.63 The allocation of responsibility for ensuring the location is in all aspects safe and suitable for the FPSO operations may be controversial. It is the Company’s location, and it may be assumed that the Company knows all that is needed about its safety and suitability; the duty placed on the FP Contractor is usually to acquaint itself with the site conditions, the point being that the FP Contractor should not be able to claim a variation order or other compensation for the consequences of unfavourable site conditions if those conditions could have been discovered and suitable provision for them being incorporated into the FPSO design.
2.64 In performing its due diligence, the FP Contractor may take account of information provided by the Company, for example its survey report of seabed conditions. To minimise risk of disputes, it is important any such report or information be categorised either as for information only or rely upon information, for the reasons described in Section C.
2.65 The obligation to prepare the site ready for FPSO operations would usually rest with the Company, including preparation of the wellheads, and obtaining all required authorisations and permits for FPSO operations at the site. The FP Contractor’s obligations concerning permits and authorisations at the site would usually relate to its own performance, and that of its subcontractors, in order to comply with local law requirements. As there may be overlap between permits required for operations at the site and for the FP Contractor’s performance, it would be usual to provide that one party is obliged to obtain all authorisations that may be required at the FPSO site except those specifically identified as being the other party’s responsibility.
Page 35
G
Page 36
Compliance with local regulations
Page 36
(i) General
2.66 The intended location of operation of the FPSO is normally known when the charter and related subcontracts are agreed. Indeed, the whole purpose of the FPSO design is to exploit a nominated field. The FPSO will be required to comply with normal maritime regulatory standards, but, as it operates as an oilfield installation, it will be required also to meet the standards applicable in that jurisdiction, which can extend to matters of fiscal metering, safety and maritime compliance. Compliance is determined by a local inspector or series of inspectors appointed on behalf of the oil and gas state. For example, in Norway, the PSA (Petroleum Safety Authority) has the overarching responsibility for safety in the petroleum industries, but it depends on the NMA (Norwegian Maritime Authority) for marine matters and the DSB (Directorate for Civil Protection) for electrical safety matters. It is usually a condition of the FPSO charter obligations that the FP Contractor should ensure that the FPSO is fully certified by the local inspectorate(s). Satisfying the requirements of the inspectorate may be difficult from a technical viewpoint and may give rise to a number of legal difficulties, including the following. 2.67 A frequent difficulty encountered in the design development process is the subjective nature of the inspector’s authority. Those conversant with regulatory requirements in shipping and shipbuilding are familiar with the approach taken by classification societies. These will certify compliance with their own rules, and, where appointed by the flag state, compliance with international regulations. During the construction and testing process, a classification representative will be asked to attend and certify that the rules and regulations have been met. This will of course depend on the adequacy of the work performed, and the suitability of design. Those involved in the design will be familiar with the classification and international regulatory requirements and will be able to incorporate these into the design as needed. The classification representative will be asked to approve the design. That approval would ordinarily be sufficient for procurement and construction to proceed in the knowledge that, provided the work complies with the approved design, the work will be duly certified. 2.68 However, where certification as an oil and gas installation is required, the process is less certain. In some jurisdictions, the only formal contact is between the oil company and the state regulators and the FP Contractor cannot control formal direct communications with the regulators. During the design process, the inspectorate may be willing to indicate its preferences and may require changes to the design to ensure, in particular, that its safety requirements are met. The classification representative may also, when approving the design, indicate whether, in its view, it would be acceptable to the inspectorate. But such an indication can be unsafe to rely on, as it is not until the later inspection (after the work has been performed) that the test of whether the FPSO design does satisfy the requirements of the inspectorate is made. If the inspection is at the shipyard, changes may be made there by the construction contractor, although these may require expensive rework and schedule delays (and there is always the prospect of a dispute over responsibility). The extent of these consequences will be even greater if the work is performed in the hull construction yard but rejected at the topsides installationPage 37
(ii) Flaring 19
2.71 The local regulations may also concern restrictions relating to flaring of gas produced from the well. This has always been a controversial issue. In the early days of offshore oil and gas production, a large proportion of the produced gas was often flared. That is obviously not currently acceptable, with the possibility that for future operations, gas flaring will be prohibited other than for emergency cases. The responsibility for mini-mising the flaring of excess gas rests primarily with the Company, under the terms of its development licence. The Company would seek to transfer some of this responsibility to the FP Contractor under the terms of the FPSO charter. Few locations allow the FP Contractor access to a gas pipeline which would receive all produced gas. There may be a requirement in the basis of design to reinject gas into the well. Some of the gas may be used for production of energy for the FPSO machinery, although it should of course be noted that the exact volume of gas to be received from the well would be difficult to predict and will vary over time. If an FPSO currently in operation does not have sufficient characteristics to allow it to achieve continuous production without resorting to flaring, it is likely, in order to achieve future carbon emission targets, that substantial modifications to the FPSO will be required. 2.72Page 38
(a) Illustration 8 – flaring
2.73 The FP Contractor agreed to implement the Company zero flaring philosophy. However, gas flaring could not be avoided during periods of processing shutdown required for repair or maintenance. The FPSO required substantial ongoing maintenance work, due to repeated failures of equipment. The FP Contractor did all it could to repair the equipment as quickly as possible, and to introduce additional preventative maintenance measures. However, in so doing, frequent periods of shutdown were required, leading to gas flaring. The Company complained this was in breach of the FP Contractor’s zero flaring obligations. The FP Contractor rejected the claim on the grounds that the relevant obligation was to ensure that all repair and maintenance work was undertaken as quickly as possible. In performing that obligation with due diligence, the FP Contractor could not be said to be in breach, as a consequence, of the zero flaring philosophy. 2.74 Going forward, it is foreseeable that the FP Contractor may be under more precise obligations relating to elimination of flaring. However, if such commitments are made, they would obviously need to be dovetailed with the FP Contractor’s obligations relating to repair and maintenance, and the capability of the FPSO as described in the basis of design.H Design changes of necessity
(i) Variation requests
2.75 Once the FP Contractor becomes aware of a change to the Company-provided design or the need for a change, it is usually required under the contractual variation mechanism in the charter agreement to give a suitable notice to the Company. This may be described as a variation request or change order request and mirrors the variation mechanism found in typical EPC/EPIC contracts.20 Incorporating into the charter variation procedures similar to those found in construction contracts is helpful to the extent that, in this way, changes occurring under both the construction contract and the FPSO charter may be kept in step. If the same procedure is followed in both the construction contract and the charter, this may make it easier for the FP Contractor to keep track of the relevant changes for the purpose of its claim for additional time and costs under the FPSO charter. However, once the variation procedure is invoked, it usually follows the same mechanism for adjusting the contract terms applicable to changes introduced byPage 39
I Preferential design changes
2.77 We turn now to changes to the design which the Company wishes to introduce. The reasons for the Company wishing to make such changes are many. For example, the Company may wish to increase the FPSO’s production capacity due to the volume of oil being greater than originally anticipated. In the current environment, the Company may wish to introduce changes to maximise fuel efficiency and reduce carbon emissions. Some of these changes may be required in order that the state regulators will grant the Company a license to develop the field. It may be necessary to make provision in the FPSO turret for future electrification by shore power. Produced water which was in the past discharged overboard after clean-up may now require to be injected intoPage 40
When instructed in writing by Company, following receipt of a Variation Request, FP Contractor shall proceed immediately as instructed notwithstanding a Variation Order has not yet been agreed.