Adjudication in Construction Law
Page 467
CHAPTER 10
Payment under the UK statutory framework
Payment under the UK statutory framework
Page 468
10.1 Stage payments and dates for payment under the Act
10.1.1 Requirements for stage payments
10.1 A party to a construction contract subject to the Housing Grants, Construction and Regeneration Act 1996 is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless it is specified in the contract that the duration of the work is to be less than 45 days, or it is agreed between the parties that the duration of the work is estimated to be less than 45 days.1 The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.2 In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.3 Every construction contract should provide an adequate mechanism for determining what payments become due under the contract, and when, and provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.4 10.2 Where a construction contract provides for interim payments to stop at the contractual date for practical completion, and there is not an express term which enables the payee to receive interim payments after the last contractual valuation there is not an implied term to that effect. It is not obvious what the proposed term would say or what would be the critical dates for serving notices. Furthermore, the proposed term is not necessary to secure business efficacy. Nor can it be said that the contract would lack commercial or practical coherence without such a term. The payee will receive full payment for its work in due course, but will have to wait until the final payment date.5 Neither does ‘any work’ in section 109(1) of the Housing Grants, Construction and Regeneration Act 1996 mean ‘every single piece of work’ so that the relevant provisions of the Statutory Scheme will apply if a construction contract fails to provide a regime of interim payments covering the whole of the work which the contractor performs. The subsection is a more general one saying that work done under construction contracts shall (except in very short projects) be subject to a regime of interim payments. Section 109(2) gives the parties considerable latitude as to the system of interim payments which they may agree. They can decide for themselves the frequency of interim payments and the amounts to be paid. For example, the parties may agree that interim payments shall be less than the full value of work done. Indeed, parties normally do agree that, so that the payer holds retentionPage 469
10.1.2 Certificates
10.4 The courts had held that under the unamended Act an adequate mechanism could include a certificate issued by a third party (for example, an architect or quantity surveyor) under a superior contract. This was thought to have caused difficulties – a sub-contractor might not be aware that a certificate had been issued in a superior contract and, where such a certificate covered work undertaken by other sub-contractors, payment to the sub-contractor was often delayed until all of the other work had been completed. Under the Act as amended, it is not an adequate mechanism for these purposes to make the determination of what payments are due, or when, dependent upon the performance of obligations in a different contract (for example, in a superior contract) or upon someone's decision as to whether obligations have been performed in a different contract.9 Under the amended legislation, if or to the extent that a contract does not contain an adequate mechanism for determining what payments become due under the contract, and when, and provide for a final date for payment in relation to any sum which becomes due, the relevant provisions of the Scheme for Construction Contracts apply.1010.2 Payment notices under the Act
10.2.1 Payer or specified person to give notice to payee
10.5 A construction contract subject to the Housing Grants, Construction and Regeneration Act 1996 as amended by the Local Democracy, Economic DevelopmentPage 470
10.2.2 Requirements for notices
10.6 A payment notice given by the payer must specify the sum that the payer considers to be or to have been due at the payment due date in respect of the payment and the basis on which that sum is calculated, which could be done, for instance, by identifying any relevant moneys paid before the payment concerned actually became payable, or by identifying any set-off or abatement applied by the payer.13 A payment notice given by a specified person must specify the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and the basis on which that sum is calculated, which could be done, for instance, by identifying any relevant moneys paid before the payment concerned actually became payable, or by identifying any set-off or abatement applied by the payer.14 A payment notice given by the payee must specify the sum that the payee considers to be or to have been due at the payment due date in respect of the payment and the basis on which that sum is calculated.15 It is immaterial that the sum is zero and such a notice is also to explain (for instance, because of any set-off or abatement) why no sum is believed to be payable.16 10.7 It cannot realistically be contended that a payment notice accurately stated the sum which the payer considered to be due at the payment due date where the covering emailPage 471
10.2.3 Effect of non-compliance
10.8 If or to the extent that a contract does not require the giving of a payment notice as specified in the Act, the relevant provisions of the Statutory Scheme for Construction Contracts apply and the consequence of this is that terms providing for the giving of a payment notice by the payer to the payee will take effect as implied terms of their contract.7 The provisions of the Statutory Scheme as to payment will only be imported and apply so as to govern the legal relations of the parties to the extent that they have not already concluded binding contractual arrangements that can remain operative. They will not automatically or necessarily be imported in their entirety. It is, of course, possible that the existing arrangements under a given contract are not capable of forming part of a payment scheme when read with the relevant provisions of the Statutory Scheme. If that were the case it may be necessary to import the Statutory Scheme's payment provisions as a whole. But that is not a necessary or correct outcome if the existing contractual arrangements are capable of co-existing with some of the payment provisions of the Statutory Scheme to form a coherent whole.1810.2.4 Hybrid contracts
10.9 Under a hybrid contract that relates to both construction operations and other matters, there can be two very different payment regimes. Although that is uncommercial, unsatisfactory and a recipe for confusion, it is the inevitable result of Parliament's desire to exclude what would otherwise have been obvious construction operations from the ambit of the 1996 Act.19 Under a hybrid contract, a notice is not a payment notice in respect of construction operations when the payee is claiming for everything, regardless of whether or not the works are construction operations within the Act. Because it is a hybrid contract, it is imperative that the payee spells out the fact that, regardless ofPage 472
Page 473
Page 474
10.2.5 Payee's notice where no payer's or specified person's notice
10.15 Where the contract requires the payer or a specified person to give the payee a notice not later than five days after the payment due date, but notice is not given as so required, the payee may give to the payer a notice at any time after the date on which the notice was required by the contract to be given.28 Where the payee gives such a notice, the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date that the notice was given.29 The effect of this new provision is to postpone the final date for payment of the sum in question by the same number of days after the date by which the payer (or specified person) ought to have given the payment notice, as the number of days after that date that the default notice was given. If, for example, a sum becomes payable on the 2nd day of the month (such that the date by which the payment notice should have been given was the 7th day) and must be paid, at the latest, on the 17th day, the effect of a payee's notice in default served on the 14th day would be to postpone the date on which the relevant sum must finally be paid to the 24th day of the month (17 + 7 = 24).30 If the contract permits or requires the payee, before the date on which the notice is required by the contract to be given, to notify the payer or a specified person of the sum that the payee considers will become due on the payment due date in respect of the payment and the basis on which that sum is calculated (what in the construction sector is known as a payee's ‘application'),31 and the payee gives such notification in accordance with the contract, that notification is to be regarded as a compliant payment notice and the payee may not give another such notice.32 10.16 The document relied upon as a notification must be in substance, form and intent an application stating the sum considered by the payee as due at the relevant due date and it must be free from ambiguity. In this context, the notification should be considered in the same light as a certificate. If there are to be potentially serious consequences flowing from it being an application, it must be clear that it is what it purports to be so that thePage 475
Page 476
10.3 Payment of notified sum under the Act
10.3.1 Withholding notices and pay less notices
10.19 As originally enacted, the Housing Grants, Construction and Regeneration Act 1996 provided that a party to a construction contract could not withhold payment after the final date for payment of a sum due under the contract unless that party had given a notice of the intention to do so (colloquially known as a ‘withholding notice'). The amendments made by the Local Democracy, Economic Development and Construction Act 2009 replace this provision in respect of withholding notices with (generally speaking) a requirement on the part of the payer to pay the sum set out in a payment notice. They also make provision for the sum in such a notice to, in effect, be challenged or revised by the giving of a type of counter-notice (colloquially known as a ‘pay less notice').3810.3.2 Payment of notified sum and pay less notices
10.20 Subject to the other requirements of the Housing Grants, Construction and Regeneration Act 1996 as amended by the Local Democracy, Economic Development and Construction Act 2009, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.39 The notified sum is the sum notified in a payment notice served by the payer, a specified person or the payee.40 This requirement to pay the notified sum is intended further to facilitate cash flow by determining what is provisionally payable. What is properly and ultimately payable as a matter of the parties’ contract is unaffected (see Rupert Morgan Building Services (LLC) Limited v Jervis).41 The payer or specified person may give notice to the payee of the payer's intention to pay less than the notified sum.42 The pay less notice must specify the sum that the payer considers to be due on thePage 477
- • from none of the information provided could the reasonable recipient work out the basis on which the zero sum figure has been calculated;
- • there is no calculation put forward which would allow the reasonable recipient to understand how that figure has been arrived at;
- • there is no specification which would allow the reasonable recipient to make any sense of the figure arrived at; and
- • the responding party sets forth no figures and thus no basis substantiating the zero sum figure in the pay less notice or in any of the other documentation upon which it relies;
it amounts to no more than saying the sum retained is not a large one and, given the number and nature of problems founded upon in the pay less notice, the cost of remedying these would clearly amount to a figure well in excess of the retained sum and thus a basis for the zero sum figure was provided. That is not providing a basis for the figure. A pay less notice in order to properly provide a basis needs at least to set out the grounds for withholding and the sum applied to each of these grounds with at least an indication of how each of these sums was arrived at.45