Practical Guide to Engineering Procurement and Construction Contracts
Page 79
CHAPTER 9
Testing the works
9.1 Introduction
This chapter describes the phase that follows when the Contractor has finished the Works and wishes to deliver the project to the Owner. At that time, he must show that the Works conform with the Owner’s specifications and he is delivering what the Owner requested. This is done by performance testing.