Transnational Construction Arbitration
Page 220
CHAPTER 14
Enforcement of DAB decisions under the FIDIC 1999 Forms of Contract
Enforcement of DAB decisions under the FIDIC 1999 Forms of Contract
Introduction
14.1 This chapter focuses on enforcement of DAB decisions under FIDIC 1999 Contracts.1 A brief introduction of Dispute Boards is given prior to focusing on the issues concerning enforcement. A simple definition of a Dispute Board is as follows: ‘A Dispute Board is a tribunal which is established to endeavour to avoid or resolve any disputes which may arise between the parties to a particular contract.’2 14.2 There are two types of Dispute Board adopted by FIDIC:- (a) A ‘standing’ dispute board which becomes familiar with a project from its inception3 and can help resolve disputes early, either informally, by giving opinions that might be adopted by the parties, or formally, by giving a binding decision following the referral process; or
- (b) An ‘ad-hoc’ dispute board, which is formed to resolve a particular dispute at the time a dispute arises between the parties.
Page 221
- (a) Members of the DAB are required to be impartial and independent of the parties8 as reflected by the consensual appointment process;9 and
- (b) the DAB’s decision is temporarily binding and should be promptly (immediately) payable by the parties.10
Page 222
The FIDIC 1999 wording
14.11 Sub-Clause 20.4 provides that:- (a) a DAB shall give a decision within 84 days (unless the parties agree to revise that period);
- (b) the decision is binding (all DAB decisions are binding);
- (c) the decision becomes final if no NOD is given with 28 days of receipt of the decision (in such circumstances the DAB’s final decision can be enforced via Sub-Clause 20.7);13
- (d) If a timely NOD is given, the DAB’s decision remains binding but is not final and the underlying dispute (‘primary dispute’) can be referred to arbitration under Sub-Clause 20.6 after expiry of the 56-day amicable settlement period.
Page 223
The issues
14.16 This chapter will focus on six issues:- (a) What is the contractual obligation of a party in relation to compliance with a DAB’s decision?
- (b) Does the ‘failure to pay’ amount to a dispute that can be referred to arbitration under Sub-Clause 20.6?
- (c) What effect, if any, does a NOD have on the contractual obligation on a party to give prompt effect to the DAB’s decision? It has been argued that the giving of a NOD absolves the paying party from complying with the DAB’s decision.
- (d) Is it necessary for the parties to refer both the primary (the merits of the underlying dispute) and secondary (dispute concerning non-payment of the DABs decision) disputes in a single arbitration?
- (e) What sort of award? Partial? Interim? Final? Provisional?
- (f) Has the wording in the Gold Book/Guidance Memorandum resolved issues?
What is the contractual obligation of a party in relation to compliance with a DAB’s decision?
14.17 This is not controversial. The wording of Sub-Clause 20.4(4) is clear: ‘The decision shall be binding on both Parties, who shall promptly give effect to it unless and until it shall be revised in an amicable settlement or an arbitral award as described below.’ 14.18 A party must promptly comply with the DAB’s decision. In a case where the DAB orders the payment of money, a contractual obligation arises to pay that money promptly.17 In South Africa, ‘promptly’ was considered to mean within 28 days of the decision being given.18Page 224
Does the ‘failure to pay’ amount to a ‘dispute’ that can be referred to arbitration under Sub-Clause 20.6?
14.19 The opening words of Sub-Clause 20.4 allow a dispute to be referred to the DAB: ‘if a dispute (of any kind whatsoever) arises between the parties in connection with or arising out of, the Contract … either Party may refer the dispute in writing to the DAB for its decision’. 14.20 In the normal course of a construction or engineering project under a FIDIC contract, the way in which a dispute arises is when one party makes a claim, the engineer rejects it in a Sub-Clause 3.5 determination and the party that wishes to pursue that claim rejects the engineer’s rejection. At that point, a dispute arises that is capable of referral to the DAB. 14.21 After a DAB has given a decision on that (primary) dispute, that same dispute can then be referred to arbitration for ‘final’ settlement under Sub-Clause 20.619 provided a NOD in relation to the DAB decision is given20 and the 56-day amicable settlement period has expired.21 14.22 There is also an obligation under Sub-Clause 20.4(4) to comply promptly with the DAB decision. If the DAB orders a party to pay and there is a failure to pay, is the dispute capable of referral under Sub-Clause 20.6 and what cause of action arises?Is the dispute capable of referral under Sub-Clause 20.6?
14.23 This issue did not trouble the Court of Appeal majority in Persero 2 but it troubled the Court of Appeal dissenting judge in Persero 2 who explored in detail whether such a dispute was referable to arbitration under Sub-Clause 20.6 as:this is not the kind of dispute contemplated by cl 20.6 because of the use of the words ‘shall be finally settled by international arbitration’ in relation to a dispute which is not settled amicably. Those words, in my view can only refer to a factual dispute such as the parties’ primary dispute. To reiterate, a dispute over a question of law cannot be settled amicably in the context of cl 20.6 – i.e. PGN and CRW cannot settle among themselves whether, as a matter of law, DAB No.3 is enforceable by an interim award pending the resolution of the primary dispute by arbitration. That dispute (viz the enforceability dispute) can only be decided by a tribunal or a court. The concept of amicable settlement in cll 20.4 and 20.5 is meant for factual disputes, and not legal disputes such as the enforceability dispute.22