Refund Guarantees
9
THE BIMCO NEWBUILDCON - Standard Newbuilding Contract - Part II, Annex A (iii) Refund Guarantee
Chapter 9.1 Standard clauses and main terms
Introduction
9.1.1
As observed in there is no single standard form of refund guarantee in universal use in the shipbuilding industry. No standard form of refund guarantee is attached to either the SAJ or AWES standard forms of shipbuilding contracts.1 Although both the Bimco NEWBUILDCON and CMAC forms require the provision of refund guarantees2 and provide by way of annex a sample form, neither has gained universal acceptance or usage.