Construction Contract Variations
CHAPTER TWO
EMPLOYER APPROVAL
EMPLOYER APPROVAL
SECTION A: INTRODUCTION | 17 |
SECTION B: EMPLOYER APPROVAL | 20 |
SECTION C: PROJECT IMPASSE | 22 |
SECTION D: COMPLEXITY IN ASSESSING RESPONSIBILITY FOR CHANGE | 29 |
SECTION E: APPROVAL VIA WAIVER AND CONCESSION | 32 |
SECTION A: INTRODUCTION
2.1
It may be the case that an employer will order variations to the scope because it changes its mind as to what it wants for aesthetic or commercial reasons. It may instead be the case that the scope defined in the contract has to be changed because the works cannot be constructed as originally planned.