Construction Contract Variations
CHAPTER THREE
SCOPE
SCOPE
SECTION A: INTRODUCTION | 33 |
SECTION B: CONTRACT INTERPRETATION | 37 |
SECTION C: CONTRACTUAL OBLIGATION TO UNDERTAKE WORK NOT EXPRESSLY REFERRED TO | 50 |
SECTION D: IMPOSSIBILITY OF BUILDNG THE DESCRIBED SCOPE | 56 |
SECTION E: BUILD RISK AND METHODOLOGY | 63 |
SECTION F: DESIGN RISK | 73 |
SECTION G: DEEMED VARIATIONS | 83 |
SECTION H: CONTRACT PROCEDURES TO RESOLVE INCONSISTENCIES | 85 |
SECTION I: CONTRACTS WITH ALTERNATIVE PRICING MODELS | 89 |
SECTION J: CONTRACTS FOR SERVICES | 97 |
SECTION A: INTRODUCTION
3.1
Construction contracts will define the scope of works that the contractor is required to undertake. In determining whether there is a variation it will be necessary to consider whether the work under review was part of that original scope.