Construction Insurance and UK Construction Contracts
Page 1
CHAPTER 1
Introduction to UK construction industry
General
1.1 In 2014, the construction industry in the United Kingdom contributed £103 billion to economic output, 6.5% of the total gross value added of the economy.1 This represents a rise of 9.5% in real terms on 2013: the largest increase since at least 1990. In the same period, construction accounted for 2.1 million jobs or 6.3% of all jobs. There can be no doubt as to the continued and growing importance of the construction industry to the UK economy. Outside these shores, the standard form JCT, NEC3 and FIDIC contracts remain the contracts of choice, often being subject to the laws of England and Wales. Contractors based in the United Kingdom undertake projects across the world: it is not possible to determine with any accuracy the contribution to the global economy, but it is clear that the contribution is both substantial and significant. 1.2 This raises the question as to what the construction industry comprises. Broadly speaking the market can be divided into housing, infrastructure, industrial and commercial sectors, with individual projects being undertaken on a private, public or public/private basis. Yet, this is a simplistic division as construction projects touch on every aspect of daily life, from the properties in which we live and work; the infrastructure (both in terms of plant and services) that provides us with water, electricity and gas; the transport networks (road, rail, airports, sea ports) that we use for work and pleasure and which ferry to our doors that which we consume: each involves construction and a construction contract. Everything in the built environment around us and more or less everything we use in daily life at some point would have made use of something built by the UK construction industry. Against that background, the risks that parties to construction contracts face, the ramifications of breach or failure; and identifying where the insuring obligations fall are matters that are often taken for granted or not analysed with sufficient detail until something goes awry. 1.3 As no two construction projects are ever the same, it is necessary to consider the individual characteristics of each project and to consider the risks at each stage of the process. Even on the most straightforward project where defects arise there is usually a debate as to whether the same is due to an error in design or workmanship and, accordingly, the identity of the ‘proper’ defendant. In turn, that requiresPage 2
- (1) liability insurance, for example public liability insurance and employer’s liability arising from claims for loss or damage;
- (2) property insurance, for example, insurance of the contract works and any material, equipment and machinery associated with it.
Valuation methods
1.8 In order to identify the form of contract most suited to a particular project, it is necessary to consider the method of procurement that is to be adopted by the employer and to identify and assess the options and risks associated with each.Lump Sum contracts
1.9 In this form, the contractor agrees a fixed price to execute certain defined building works. The figure is usually arrived at by way of the bill of quantities and is agreed at the time of contract formulation when the work is also commenced. AllPage 3
Measurement Contracts
1.10 The contract sum for a measurement contract (also known as a re-measurement contract) is not finalised until the project is completed. The process involves the employer (usually through his consultants) preparing as part of the tender documents a bill of quantities where quantities are estimated rather than finalised. The contractor prices against each item in the bill, providing a unit rate in respect of each bill item. During the project the actual quantity of works in respect of each item in the bill is measured and the quantity agreed, to which the contractual rate is applied to build up the final contract value. Accordingly, at the outset there is a contract sum that is not a finalised figure and is subject to the works being re-measured at completion. As such, by definition it cannot be a lump sum contract. 1.11 Where works are instructed in respect of which there is no applicable rate, the contractor can build up new rates or “star rates”, which will then be used in the valuation of the works.Cost Contracts
1.12 With a cost contract there is no binding, pre-agreed sum contract sum. The contractor is entitled to be paid whatever the work(s) actually cost(s), together with an additional payment normally called a management fee, which should cover its profit and overheads. An example is the JCT Prime Cost Contract 2011. This form of contract is often adopted where the employer requires an early start on site such that there is insufficient opportunity to prepare a detailed design and bill of quantities against which a contractor can price. 1.13 There are four common variations:- (1) Cost plus a percentage: the contractor is paid the actual cost of work reasonably incurred, plus a fee which is a percentage of the actual cost.
- (2) Cost plus fixed fee: the fee is a fixed lump sum and so the contractor has an incentive to complete.
- (3) Cost plus fluctuating fee: an estimate of the total cost is made and the fee varies according to actual cost.
- (4) Target cost based on the bill of quantities and compared with actual adjusted target cost. If the actual cost shows a saving (or an increase), the fee is increased (or reduced) appropriately.
Procurement Methods
1.14 The four most commonly used methods of procurement are considered below.
Page 4
Traditional/Conventional
Page 4
Approach and Standard Form
1.15 This form of procurement has been standard practice since the mid-nineteenth century. There are two defining features of the traditional/conventional method of procurement:- (a) The employer will engage a professional team to prepare a full package of documents (usually comprising a specification, drawings, contract particulars that set out the particulars of the contract to be entered into and any amendments to those contract terms, bill of quantities (where appropriate) and, if they have been obtained, copies of any ground investigation or soil reports). That package of information is then supplied by the employer to those contractors who are to be invited to submit a tender in respect of the works described in the tender documents.
- (b) It follows that the design process is separate from the construction process, and usually the contractor will have no responsibilities as regards design.
Responsibility and Risk
1.18 Due to the fact that a full package of documents needs to be supplied as part of the tender process, time needs to be available for those documents to be adequately prepared. Experience shows that where employers seek to rush this phase, errors are inevitably made either as to design or specification or both. This also means that the project life tends to be longer as the design and construction phases are undertaken sequentially by different entities. However, because the employer appoints the consultants that undertake the design - whether architect or engineer - it means that the employer retains full control over the design process. 1.19 Furthermore, because the invitation to tender is usually sent to a number of contractors, there is a competitive tendering process such that the employer can be confident that he is getting a good price for the works. Where there is no competitive tender it is common for there to be a negotiated contract price, again providing for certainty as to the project cost (although the cost can be increased or decreased later in the event that works are varied). 1.20 Subject to the terms of the contract, the contractor is responsible for supplying the labour and materials necessary to complete the works and accordingly for the quality of goods and workmanship. As he does not (usually) bear design responsibility,2 hePage 5
Design and Build/Contractor’s Design Portion/Turn Key
Approach and Standard Form
1.22 In this method of procurement the contractor is responsible for undertaking both the design (or some element of the design) and the construction of the works for an agreed lump sum price. It is a matter for the employer as to whether the whole project will be procured on a design and build basis, or whether only certain elements will be. It follows that this method of procurement provides flexibility and can be particularly useful where one element of the works involves a proprietary system or element. 1.23 Where the contract is on a full design and build basis, the employer will engage a professional team to undertake outline design (often also securing planning permission) and an outline specification which forms the “employer’s requirements”. Whilst this will not be as detailed or as time consuming as the pre-tender process under the traditional method, again sufficient time needs to be allowed for this process to be undertaken. 1.24 Thereafter, the contractor is responsible for undertaking the detailed design so as to produce a final product that meets the employer’s requirements as defined. In order to evaluate tenders that are submitted, contractors are usually required to provide detailed “contractor’s proposals” that set out how the contractor intends to fulfil the design brief. Again, sufficient time needs to be allowed for this process to be completed so the employer has comfort that its employer’s requirements have been met. It is vital that the employer’s advisers consider the contractor’s proposals with care so as to ensure no mismatch between the two. 1.25 Whether at the stage of preparing the contractor’s proposals, or during the detailed design during the works, a contractor will often subcontract out the design to specialist subcontractors - for example in relation to the mechanical and electrical elements of the works. However, the contractor remains responsible for the design visà-vis the employer. In many instances the contractor will engage the employer’s consultants under a novation agreement, thereby ensuring continuity of design process. 1.26 An example of the standard forms of contract appropriate to this form of procurement is the JCT Design and Build Contract 2011 (DB2011). 1.27 It is also open to an employer to procure works on the basis of a turnkey contract, where a contractor offers to build in accordance with his own standard design: in this scenario the employer has little if any design input at all3: he relies upon the contractor both for design and construction of the finished project.Page 6
Responsibility and risk
1.29 Subject to the terms of the contract, the contractor will be responsible for ensuring the adequacy of his design (or that portion of the design that he is responsible for) and in this respect he is likely to have the same responsibility as an architect or engineer would have to the employer. However, most of the standard form contracts carve out responsibility where there is a deficiency in the employer’s requirements that results in loss or damage being suffered; although this is often subject to a requirement that the contractor notify any such deficiency once detected so as to minimise the consequences of the said deficiency. 1.30 Unlike the traditional method, an employer does not retain finite control over the design; once the contract is let the detailed design is a matter for the contractor. It will be a matter for individual employers as to the degree of control they wish to retain. 1.31 The contractor will also be responsible for ensuring the quality of goods and workmanship that he supplies. As such, in the event of any deficiency in the design of the works (or the contractor’s design portion as applicable), the contractor will bear the cost of remedying the same. In the event that the contractor has subcontracted the design (or any element thereof) he may have a claim down the line against the actual designer - subject to an insurance provision that prevents the subrogation of such claims. 1.32 From the employer’s perspective the design and build or turnkey contracts offer the most certainty as to price and in the event of a defect in the works, there is (save for any deficiency in the employer’s requirements) only one “target”: the contractor. Thus, any difficulties in identifying whether it is a design or workmanship issue fall away. The caveat is that the liabilities in respect of design and workmanship are likely to be different, depending on the terms of the contract. Furthermore, as design and build contracts are lump sum contracts the employer has certainty as to price, subject to any variations that may be instructed. As such, design and build contracts are a relatively low risk option for an employer.Management
Approach and standard form
1.33 Management procurement takes two forms:- (1) Management Contracts
- (2) Construction Management.
Page 7
Responsibility and risk
1.39 From the foregoing it will be apparent that the employer bears the lion’s share of the risk in respect of management procurement as regards time and cost. However, the employer retains control over matters of design and quality throughout the project through its professional team. It is particularly suitable where the works involve specialist design elements that can be let as discrete works packages. It is a low risk option for the management contractor and the construction manager given the limited role which is to be performed.Integrated
Approach and standard form
1.40 Also known as partnering or collaborative procurement, integrated procurement has become increasingly popular in recent years. It was developed in responsePage 8
Responsibility and risk
1.43 The fundamental principle of collaborative procurement is that risk is minimised and responsibility shared as appropriate to the particular project.Contract forms
1.44 Leaving to one side bespoke contracts developed for individual projects, there are now three main suites of contracts available for contracting parties to choose from:7- Joint Contracts Tribunal (“JCT”) Suite, the current edition being that issued in 2011;8
- The New Engineering Contract or “NEC” Suite, the current edition being the 2013 edition;9
-
Page 9
Consultancy agreements and collateral warranties
1.48 As well as determining the appropriate method of pricing and procurement, an employer needs to consider whether his interests are safeguarded as regards the services provided by the professionals involved in the project, where those professionals have not provided services direct to the employer. This issue is addressed by requiring the relevant professional to enter into a collateral warranty for the benefit of the employer. Similarly, funders, purchasers, freeholders and tenants may need to consider whether they have a right of recourse against both contractor and design professionals given the rule against recovery in cases of pure economic loss.11 1.49 It is now a common expectation that all consultants, together with the relevant contractors and subcontractors, will enter into contracts that give direct rights to the ultimate beneficiaries of the development (the identity of the beneficiaries may not yet be known, but they may comprise lenders to the development, and purchasers or tenants of the completed development). However, it is equally common that those collateral warranties are not executed; that can give rise to disputes as to the party that bears responsibility for the failure to procure the collateral warranties.
1 House of Commons Briefing Paper “Construction Industry: Statistics and Policy” 6 August 2015, Chris Rhodes.