MIRANT ASIA-PACIFIC CONSTRUCTION (HONG KONG) LTD AND ANOTHER v OVE ARUP & PARTNERS INTERNATIONAL LTD AND ANOTHER (No 3)
[2008] BLR 304
QUEEN’S BENCH DIVISION (TECHNOLOGY AND CONSTRUCTION COURT)
Before Mr Justice Jackson
Procedure - Security for costs - Return of money paid into court as security - Material change of circumstances - Reorganisation of corporate structure and improvement of financial position of parent companies - First claimant successful on liability - Payment into court by defendants and subsequent increases in sums paid in - CPR 25.13.