Appendix C

Adjudication Rules

Adjudication Rules

1. JCT Rules for Adjudication RULES FOR ADJUDICATION For use with the JCT Building contract for a home owner/occupier and JCT Consultancy agreement for a home owner/occupier Generally
  • 1. These adjudication rules apply to disputes which arise between the customer and the contractor (sometimes referred to as the parties) under the Building contract for a home owner/occupier (“the building contract”). These adjudication rules also apply to disputes between the customer and the consultant under the Consultancy agreement for home owner/occupier. Where this is the case the rules shall be read with ‘the consultancy agreement’ being substituted for ‘the building contract’ and ‘consultant’ being substituted for ‘contractor'.
  • 2. The customer or the contractor can apply for adjudication on any dispute which arises under the building contract from the date the work starts until 6 years after it has finished.
  • 3. An adjudicator can be appointed either by the Royal Institution of Chartered Surveyors (RICS), the Royal Institute of British Architects (RIBA) or the National Specialist Contractors Council (NSCC). Each of these bodies is called an appointing body.
Applying for an adjudicator
  • 4. If the customer or the contractor wants to have a dispute decided by an adjudicator he must complete the application form and send it with a payment of £144.00

    Page 558

    (inclusive of VAT)1 to one of the above appointing bodies2 [2]. (The payment covers the appointing body's administration costs).
  • 5. Within 48 hours of receiving the application the appointing body will confirm receipt in writing to both customer and contractor.
  • 6. The appointing body will appoint an adjudicator within 7 days of giving written confirmation of receipt of the application.
  • 7. If the customer and the contractor have each applied for adjudication about the same dispute, but each has applied to a different appointing body, the adjudicator will be appointed by the appointing body whose date of confirmation of receipt of the application is the earlier.
  • 8. If either the customer or the contractor applies for adjudication but the other person starts court proceedings about the same dispute, the adjudication can still go ahead pending settlement of the dispute by the court.
  • 9. Once an adjudicator is appointed the role of the appointing body is at an end, and all further communications must be made directly to the adjudicator.
Costs of adjudication
  • 10. The adjudicator will charge an hourly fee for his services. He will tell the customer and the contractor, before he begins the adjudication process, what his fee will be. The amount of fee will depend on the complexity of the issues in dispute, but will not exceed £150 per hour (exclusive of VAT) up to a maximum of 15 hours. This is regardless of how many additional hours the adjudicator actually spends on the adjudication.
  • 11. When he makes his decision the adjudicator will state whether the customer or the contractor is to be responsible for paying his fees, or whether payment is to be divided between them in a proportion that the adjudicator decides.
  • 12. The adjudicator can also order that the application payment of £144.00 made by one party should be reimbursed to him by the other party.
  • 13. If the party responsible for paying any or all of the adjudicator's fees does not pay them, the adjudicator can take court proceedings against that party to recover the amount not paid. The adjudicator will not claim that unpaid amount from the other party.
  • 14. The customer and the contractor will be responsible for their own costs in preparing for the adjudication, e.g. costs for professional advice and getting documents together.
Powers and duties of the adjudicator
  • 15. As soon as possible after his appointment the adjudicator will notify the customer and the contractor that he will be carrying out the adjudication. At this point he may ask them for information about the dispute.

  • Page 559

    16. The adjudicator will act fairly between the customer and the contractor, and will carry out the adjudication by reference to the terms of the building contract.
  • 17. If he wishes, the adjudicator can visit the premises where the work has been carried out. The visit will be at a time when both the customer and the contractor are expected to be present. During the visit the adjudicator can examine the work. He can ask questions about the dispute. The customer and the contractor will co-operate with the adjudicator and give any information he needs.
  • 18. If either party chooses not to be present when the adjudicator visits the premises, the adjudicator can go ahead in their absence.
  • 19. If the dispute is about payment, the adjudicator can order the customer to pay the contractor, with interest, any amount which he decides is appropriate. The adjudicator can also order the contractor to repay the customer, with interest, any money which he decides is appropriate. The rate of interest will be no more than 5% per annum above the official dealing rate of the Bank of England current at the date when the adjudicator considers that interest should apply and will run for such period as the adjudicator thinks fit.
The adjudicator's decision
  • 20. The adjudicator will give his decision in writing no later than 21 days after being appointed. He will send a copy of his decision to the customer and the contractor.
  • 21. The adjudicator is not required to give reasons for his decision.
  • 22. The customer and the contractor must follow the adjudicator's decision as part of their obligations under the building contract, unless and until either party obtains a court judgment about the dispute which is different from the decision of the adjudicator.
Application forms to appoint an adjudicator are available from:
  • The Royal Institution of Chartered Surveyors
  • Dispute Resolution Service
  • Surveyor Court
  • Westwood Way
  • Coventry
  • CV4 8JE
  • Phone: 020 7222 7000
  • Fax: 020 7334 3802
  • E-mail: drs@rics.org
  • or
  • Royal Institute of British Architects
  • Adjudication Administrator
  • 66 Portland Place
  • London
  • W1N 4AD
  • Phone: 020 7307 3649

  • Page 560

    Fax: 020 7307 3754
  • Email: adjudication@inst.riba.org
  • or
  • National Specialist Contractors Council
  • 6-8 Bonhill Street
  • London
  • EC2A 4BX
  • Phone: 0844 249 5351
  • Fax: 0844 249 5352
  • E-mail : enquiries@nscc.org.uk

Adjudication under the JCT Building contract for a home owner/occupier and JCT Consultancy agreement for a home owner/occupier

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2024 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.