Law of Shipbuilding Contracts
Page 389
Index
Index
- Abatement
- Acceptance of breach
- Acceptance of vessel
- Acts of God
- Additional funding
- Adjustment of contract price
- AFS 2001 see Anti-Fouling Systems on Ships Convention 2001
- Allocation of design risk
- Alternative dispute resolution
-
Ancillary agreements
- completion bonds, –
- contract and refund guarantee assignments, –
- guarantees issued on behalf of builder
- guarantees issued on behalf of buyer
- introduction,
- letters of comfort, –
- options, –
- performance guarantees, –
-
Page 390
- specifications, –
- Anti-bribery
- Anti-Fouling Systems on Ships Convention 2001
- Appeals
- Applicable law
- Appointment of buyer’s representatives
- Approval of plans and drawings
-
Arbitration
- alteration of delivery date
- alternative dispute resolution, and, –
- appeals
- Brussels I Regulation, and,
- description and class, and,
- entry in court
- expenses
- Hague Convention, and,
- introduction,
- judicial proceedings, and
- London, in
- Lugano Convention, and,
- modifications, and, –
- non-technical disputes
- notice of award
- proceedings
- standard form provisions,
- technical disputes
- text of SAJ Form,
- Assignment
- AWES Form
- Bank charges
- Bill of sale
- BIMCO, see also NEWBUILDCON
- Bridging contracts
- Brussels I Regulation
-
Builder
- breach of contract, and, –
-
Page 391
- negligence, and,
- Builder’s bonus
- Builder’s certificate
- Builder’s credits
- Builder’s guarantees
- Builder’s guarantees enforceability
- Builder’s liabilities
- Builder’s lien
- Builder’s risks
-
Builder’s warranty
- circumstances outside builder’s control,
- consequential losses, –
- damage caused to vessel, –
- defects identified at delivery,
- exclusion of liabilities, –
- express terms, –
- extent of builder’s responsibility,
- guarantee,
- guarantee engineer
- implied terms, –
- limitations
- loss of use,
- nature, –
- notice of defects requirement
- notice requirement
- obligation to remedy
- replaced parts,
- special losses, –
- subcontractors’ warranties, –
- text of SAJ Form, –
- time limits,
- unfair terms, –
- reasonableness, –
- Bunker Convention Certificate
- Buyer
- Buyer’s allowances
-
Page 392
- Buyer’s default
- Buyer’s remedies
- Buyer’s representatives
- Buyer’s supplies
- Cancellation
- Cargo Ship Safety Construction Certificate
- Cargo Ship Safety Equipment Certificate
- Cargo Ship Safety Radio Telegraphy (or Telephony) Certificate
- Characteristics of vessel
- China Maritime Arbitration Commission, see also CMAC Form
- Choice of law
- Classification certificate
- Classification of vessel
- CMAC Form
- COLREG 1972, as amended
- Community of European Shipyards’ Association
- Completion
- Completion bonds
- Completion of contract works
- Compliance with plans and drawings
- Concurrent delays
- Condition of vessel
- Conditions precedent and subsequent
- Conduct of trials
-
Page 393
- Consent
- Consequential losses
- Consumable stores protocol
- Continuous Synopsis Record
- Contract assignments
-
Contract price
- abatement rights, –
- additional funding, –
- adjustment of see also Adjustment of contract price
- bank charges,
- builder’s credits
- buyer’s allowances, –
- buyer’s credits, –
- currency, –
- deduction, –
- design and supply of drawings,
- financing for the builder
- financing for the buyer
- financing the newbuild
- instalment payments, –
- introduction, –
- method of payment, –
- prepayment,
- renegotiation, –
- security, –
- set-off, –
- subsidies
- terms of payment
- text of SAJ Form, –
- timing of payment, –
- Contractor’s warranty
- Control of Harmful Anti-Fouling Systems on Ships Convention 2001
- Copyright
- Corruption
- Crewing
- Currency
- Damage to the vessel
- Damages
- Deadweight
- Deduction
- “Deemed” delivery
-
Default of buyer
- common law remedies, –
- damages,
- definition
- effect
- interest and charge,
- introduction,
- notice,
-
Page 394
- rescission by builder, and
- sale of vessel
- text of SAJ Form, –
- Defects
-
Delay in delivery
- builder’s breach of contract or negligence, –
- causes
- concurrent delays,
- events see also Force majeure
- excessive delay
- extension of time, –
- force majeure see also Force majeure
- insurance, and,
- introduction, –
- liquidated damages, and
- negligence, –
- notice, –
- permissible delay
- prior breaches, –
- rescission for excessive delay
- text of SAJ Form, –
-
Deliverability
- application of general principles
- compliance with description, –
- conditions, –
- fitness for purpose, –
- general principles
- introduction, –
- NEWBUILDCON, –
- principles of construction, –
- reasonable fitness for purpose, –
- rejection of goods on quality grounds, –
- SAJ Form, –
- satisfactory quality, –
- statutory implied terms excluded by contract terms, –
- statutory implied terms not excluded by contract terms
- warranties, –
-
Delivery, see also Institute Clauses for Builders’ Risks (1/6/88)
- acceptance protocol,
- bill of sale,
-
Page 395
- builder’s lien,
- classification certificate, –
- commercial invoice,
- condition of vessel, –
- consumable stores protocol,
- “deemed”,
- delay, and see Delay in delivery
- deliverability, and see Deliverability
- documentation see Documentation
- documents to buyer
- drawings,
- early delivery,
- effect of lex situs, –
- fuel oil protocol,
- introduction,
- inventory protocol,
- invoice,
- method
- non-registration certificate,
- place
- plans,
- removal from shipyard,
- risk of loss or damage, –
- tender of vessel
- time
- title to vessel
- trading certificate, –
- trials protocol,
- vessel’s condition, –
- warranty of freedom from encumbrances, –
-
Description and class clause
- characteristics, –
- classification requirements
- compliance with plans and drawings,
- dimensions, –
- dispute resolution,
- environmental requirements, –
- hull number, –
- introduction,
- performance guarantees, –
- quality standards and assurance, –
- registration,
- regulatory requirements
- subcontracting, –
- text of SAJ Form, –
- Description of goods
- Design risk allocation
- Dimensions
- Discharge of obligations
- Discrepancies
-
Dispute resolution
- alteration of date
- alternative dispute resolution, –
- appeals
- arbitration in London
- Brussels I Regulation, and,
- description and class, and,
-
Page 396
- expenses
- Hague Convention, and,
- introduction, –
- judicial proceedings
- Lugano Convention, and,
- modifications, and, –
- non-technical disputes
- notice of award,
- proceedings,
- standard form provisions,
- technical disputes
- text of SAJ Form, –
-
Documentation
- delivery, and
- acceptance protocol, –
- bill of sale,
- builder’s certificate,
- classification certificate, –
- consumables stores protocol,
- drawings,
- fuel oil protocol,
- inventory protocol,
- invoice,
- lube oils protocol,
- non-registration certificate,
- plans,
- protocol, –
- trading certificate, –
- trials protocol,
- warranty of freedom from encumbrances, –
- delivery, and
- Drawing approvals
- Drawings
- Duties
- Early delivery
- Effective date of contract
- Energy Efficiency Design Index (EEDI)
- Entire agreement
- Environmental protection
- Environmental requirements
- Equipment defects
- Equipment shortage
- Excessive delay
- Excessive fuel consumption
- Exclusion of liabilities
- Exclusion of liability
- Expenses
- Explosions
- Express terms
- “Financial” defaults
-
Financing
- builder, and
-
Page 397
- buyer, and
- buyer’s credits,
- instalment payments, –
- introduction,
- leasing, –
- newbuild, the
- subsidies
- Fitness for purpose
-
Force majeure
- causation
- delaying events
- accidents beyond control of builder, –
- acts of God, –
- acts of princes or rulers,
- caused by other commitments, –
- defects in equipment, –
- defects in machinery, –
- defects in materials, –
- delay in vessel construction, and, –
- delays in delivery, and, –
- equipment shortage, –
- explosions,
- hostilities, –
- impact, –
- labour disturbances, –
- labour shortage, –
- lockouts, –
- other delaying events, –
- requirements of government authorities,
- SAJ Form,
- shortage of equipment, –
- shortage of machinery, –
- shortage of materials, –
- strikes, –
- war, –
- equipment defects,
- equipment shortage, –
- excessive delay,
- frustration, –
- general principles
- impact of delaying events, –
- introduction, –
- machinery defects,
- machinery shortage, –
- materials defects,
- materials shortage, –
- notice of delay
- permissible delays
- “prevention principle”, –
- rescission for excessive delay
- ship conversion contracts,
- text of SAJ Form, –
- Formation of contracts
- Frustration
- Fuel consumption
- Fuel oil protocol
- Future instalments
- Goal-based Ship Construction Standards
- Governing law
-
Page 398
- Guarantee engineer
- Guarantees
- Implied terms
- Inadequate deadweight
- Inception of project
- Innominate terms
- Instalment payments
- Institute Clauses for Builders’ Risks (1/6/88)
- Insufficiency of speed
-
Insurance
- application of recovered amount
- assignment,
- “builders’ risks”,
- buyer’s supplies,
- cancellation,
- delay in delivery,
- duty to insure, –
- extent of coverage
- introduction,
- Japanese Builder’s Risks Clause
- latent defects, –
- partial losses, –
- ship conversion contracts,
- termination of builder’s obligation
- text of SAJ Form, –
- total loss, –
- Intellectual property rights
- Interest
- International Air Pollution Prevention Certificate
- International Anti-fouling System Certificate
- International Sewage Pollution Prevention Certificate
- International Ship Security Certificate
-
Interpretation clause
- applicable law
- discrepancies,
- entire agreement
- express exclusions of liability for misrepresentation,
- general principles of interpretation, –
- generally, –
-
Page 399
- text of SAJ Form,
- text of SAJ Form,
- Inventory protocol
- Invitations to tender
- Invoice
- ISM Code
- ISO 9000
- Labour disturbances
- Labour shortage
- Latent defects
- Leasing
- Letters of comfort
- Letters of intent
- Lex situs
- Limitation of liabilities
- Liquidated damages
- Load Lines Convention 1966
- Location
- Lockouts
- Loss of use
- Losses
- Lugano Convention
- Machinery defects
- Marine Construction All Risks (01/09/07)
- Maritime Labour Convention 2006 (ILO),,
- MARPOL 73/78
- Materials
- Milestone events
-
Modifications
- builder, by
- buyer, by
- class, of
- declaration and acceleration of work,
- dispute resolution, –
- introduction,
- offshore contracts, –
- specifications, of
- builder, by, –
-
Page 400
- dispute resolution, –
- generally,
- text of SAJ Form,
- substitution of materials,
- text of SAJ Form, –
- variation procedures, –
- Navigation
- Negligence
- Negotiation of contracts
-
NEWBUILDCON
- adjustment of contract price
- allocation of design risk,
- anti-bribery,
- applicable law,
- approval of plans and drawings,
- assignment,
- background,
- builder’s warranty, and, –
- buyer’s default
- buyer’s representatives
- buyer’s supplies, –
- certificate of non-registration,
- classification certificate, –
- classification requirements,
- condition of vessel, –
- conditions precedent and subsequent,
- conduct of trials
- confidentiality,
- consequential losses,
- contract price
- corruption,
- currency,
- damage caused to the vessel,
- deliverability, –
- delivery of vessel
- discrepancies,
- dispute resolution
- duties,
- entire agreement
- environmental protection, –
- exclusions of liability, –
- explosions,
- force majeure,,
- hostilities,
- implied terms,
- insurance
- intellectual property rights,
- interpretation clause
- applicable law,
- discrepancies,
-
Page 401
- “non-reliance” provisions, –
- limitations of liability, –
- liquidated damages,
- lock-outs,
- loss of use,
- modifications
- “non-reliance” provisions, –
- notice,
- notification of defects,
- passing upon delivery and acceptance,
- payment of price
- performance guarantees,
- preamble,
- property in plans and drawings,
- provisioning,
- quality standards and assurance, –
- quality warranty, and
- refund guarantees,
- registration,
- regulatory requirements,
- replaced parts,
- rescission by buyer
- sale of vessel,
- set-off and deduction,
- special losses,
- strikes,
- subcontracting,
- suspension of the work, –
- taxes,
- text, –
- title to vessel
- trading certificate, –
- trials
- unfair terms,
- war,
- weather conditions,
- Non-registration certificate
- Notice
- Notification of defects
- Novation
- OECD framework
- Offshore contracts
- Options
- Partial losses
- Parties
- Passenger Ship Safety Certificate
-
Patents
- drawings
-
Page 402
- plans
- specifications,
- text of SAJ Form,
- Payment
- abatement rights, –
- bank charges,
- currency, –
- deduction rights, –
- instalments, –
- method, –
- prepayments,
- security, –
- set-off rights, –
- terms
- timing, –
- Performance guarantees
- Permissible delay
- Place of delivery
- Plan approvals
- Plans
- Preamble
- Prepaid instalments
- Prepayment
- Presentation of results
- Prevention of Collisions at Sea Convention 1972 as amended
- Prevention of Pollution from Ships Convention 1973 as amended
-
Price
- abatement rights, –
- additional financing, –
- adjustment of see also Adjustment of contract price
- bank charges,
- builder’s credits
- buyer’s allowances, –
- buyer’s credits,
- currency, –
- deduction, –
- design and supply of drawings, and,
- financing for the builder
- financing for the buyer
- financing the newbuild
- instalment payments, –
- introduction, –
- method of payment, –
- prepayment,
- renegotiation, –
- security,
- set-off, –
- ship conversion contracts, –
- subsides
- terms of payment
- text of SAJ Form, –
- timing of payment, –
- Prior breaches
- Provisioning
-
Page 403
- Quality standards
- Quality warranty see Warranty of quality
- Radio Station Licence
- Reasonable fitness for purpose
- Refund by builder
- Refund guarantees
- Registration
- Regulatory requirements
- Rejection of goods
- Rejection of vessel
- Remedies
- Removal from shipyard
- Renegotiation
- Replaced parts
- Representatives
- Repudiation
- Rescission by builder see also Buyer’s default
-
Rescission by buyer
- acceptance of builder’s repudiatory breach, –
- buyer’s remedies
- buyer’s right
- buyer’s supplies,
- common law remedies
- damages, –
- delay in delivery, and
- discharge of obligations
- effect
- excessive delay, and
- financial defaults,
- force majeure
- grounds
- introduction, –
- liquidated damages, and
- loss of rights, –
- losses,
- notice
-
Page 404
- specific performance, –
- technical deficiencies,
- text of SAJ Form,
- title to vessel,
- total loss of vessel,
- Risk of loss
- Rome I Regulation
- Safety of Life at Sea Convention 1974 as amended see also SOLAS 1974
- Safety Management Certificate
-
SAJ Form see also under individual headings
- allocation of design risk,
- approval of plans and drawings, –
- assignment,
- background,
- buyer’s default, –
- buyer’s supplies,
- contract price
- default by buyer, –
- delays, –
- delivery
- description and class, –
- dispute and arbitration
- effective date of contract,
- force majeure,, –
- guarantee,
- inspection, –
- insurance
- intellectual property rights,
- interpretation,
- modifications, –
- notice,
- preamble,
- quality warranty, –
- rescission by buyer,
- sundry provisions,
- taxes and duties,
- terms of payment, –
- trials, –
- warranty of quality, –
- Sale of goods legislation
- Sale of the vessel
- Satisfactory quality
- Scope of works
- Sea trials see Trials
- Sector Understanding on Export Credits for Ships
- Security
- Set-off
- Settlement of builder’s liability
- Ship conversion contracts
- Ship Energy Efficiency Management Plan
- Ship Security Plan
- Shipbuilders’ Association of Japan see also SAJ Form
-
Shipbuilding contracts
- formation
- nature
- negotiation
- bridging contracts, –
- date of contract,
- final meeting,
- inception of project, –
- initial negotiations,
- introduction,
-
Page 405
- letters of intent, –
- NEWBUILDCON,
- other forms,
- SAJ Form,
- standard forms, –
- specifications, –
- terms
- Shortages
- SOLAS 1974
- Special losses
- Specific performance
- Specifications
- Speed
- Standard forms of contract
- Statutory implied terms
- Steel cutting
- Strikes
- Subcontracting
- Subsidies
- Substitution of materials
- Sundry provisions
- Surplus consumable stores
- Suspension of the work
- Taxes
- Technical deficiencies
- Technical disputes
- Tender of vessel
- Terms of payment
- Third party rights
- Time of delivery
- Time limits
-
Title to vessel
- builder’s lien,
- effect of English law
-
Page 406
- introduction,
- rescission by buyer, and,
- text of SAJ Form,
- Title to works
- Tonnage Measurement Convention 1969
- Total loss of vessel
- Trademarks
- Trading certificate
- Trial protocol
-
Trials
- acceptance of vessel
- completion,
- conduct
- crewing, –
- deliverability
- application of general principles, –
- compliance with description, –
- conditions, –
- construction, –
- general principles, –
- innominate terms, –
- introduction, –
- principles of construction, –
- reasonable fitness for purpose, –
- rejection of goods on quality grounds, –
- satisfactory quality, –
- statutory implied terms excluded by contract terms, –
- statutory implied terms not excluded by contract terms, –
- warranties, –
- disposition of surplus consumable goods
- effect of acceptance
- introduction, –
- location,
- method of acceptance
- navigation, –
- notice,
- offshore contracts,
- presentation of results,
- provisioning, –
- rejection of vessel
- text of SAJ Form, –
- weather conditions
- Unfair contract terms
- Unpaid instalments
- Variation of contract price, see Adjustment of Contract Price
- Variation procedures
- Vessel’s condition
- War
- Warranties
- Warranty of freedom from encumbrances
-
Page 407
- circumstances outside builder’s control,
- consequential losses, –
- damage caused to the vessel, –
- defects existing on delivery,
- exclusion of liabilities
- express terms, –
- extent of builder’s responsibility,
- guarantee,
- guarantee engineer
- implied terms, –
- introduction, –
- limitations
- loss of use,
- nature, –
- notice of defects requirement
- notice requirement
- obligation to remedy
- replaced parts, –
- special losses, –
- subcontractors’ warranty, –
- text of SAJ Form, –
- time limits,
- unfair contract terms
- unfair terms
- Weather conditions