Construction Insurance and UK Construction Contracts
Page 336
CHAPTER 26
IChemE Lump Sum (Red Book), Reimbursable (Green Book) and Burgundy (target cost) Contracts
General
26.1 The Institution of Chemical Engineers (“IChemE”) publish two suites of contracts (contracts for use within the UK and for use overseas) which, like the FIDIC contracts, are referred to by the colour of the cover with which the contract is bound. The contracts are tailored to the design, construction and delivery of process plants and equipment and are very much “performance based”: Clause 3.4 imposes an obligation that the “plant as completed by the Contractor shall comply with the Contract and shall be in every respect fit for the purpose it was intended”. 26.2 In 2013, IChemE overhauled all of its contracts, save for Yellow Book: this change is to be welcomed as it has resulted in a more cohesive contract, particularly as regards the allocation of risk and insurance. The IChemE contracts in the UK suite of contract are:- Form of Contract for Lump Sum Contracts: Red Book 5th Edition (2013) Form of Contract for Reimbursable Contracts: Green Book 4th Edition (2013) Form of Contract for Target Cost: Burgundy Book 2nd Edition (2013) Subcontract (compatible with Red, Green and Burgundy): Yellow Book 4th
- Edition (2013)
- Civil Engineering Subcontract (compatible with Red, Green and Burgundy):
- Brown Book 3rd Edition (2013)
- Minor Works (to existing plant): Orange Book 2nd Edition (2003).
- the Agreement;
- the Special Conditions (if any);
- the General Conditions of Contract (1-49);
- the Specification; and
- the Schedules to be compiled individually for each Contract (1-21).
Page 337
IChemE Red, Green and Burgundy Books insurance provisions: General
26.5 The clauses relevant to risk and insurance are:- Clause 30: Care of the Works; and
- Clause 31: Insurance.
Specific clauses
(a) Plant, site materials and temporary works
Risk allocation
26.6 By clause 30.3, the plant and temporary works are under the care and control of the contractor until the purchaser takes over the plant (as defined by clause 33.7). However, the contractor’s obligation to make good any loss or damage is subject to the provisions of clauses 30.4 to 30.7. Where words are emboldened, they are defined terms within clause 1 of the conditions.
30.4 Subject to Sub-clause 30.8, the Contractor shall make good any loss or damage to the Plant, Site Materials and Temporary Works that may occur: